The Subdivision Process


While every City or County may have its own unique process of subdividing property, most follow a similar general format. I have tried to layout how a typical plot of property might make its way from raw land to finished residential lots.

From Wikipedia
Subdivision is the act of dividing land into pieces that are easier to sell or otherwise develop, usually via a plat. The former single piece as a whole is then known as a subdivision in the United States. If it is used for housing it is typically known as a housing subdivision or housing development, although some developers tend to call these areas communities.
Subdivisions may also be for the purpose of commercial or industrial development, and the results vary from retail malls with independently owned out parcels to industrial parks.


The Subdivision Process

Phase I: Feasibility & Preliminary Preparation
• Review and Research Existing Data & Maps. Recon by consultants as necessary (wetlands, soils etc)
• Initial review of Zoning, Access, Topography, Utilities, Market
• Meet with Jurisdictions
• Preliminary Proforma & Schedule
• Internal Feasibility Results. Proceed or Halt project
• Initial Planning, Hire Engineer
• Field Work (at least enough for submittal): Survey, Mapping, Prelim. Engr., Critical Area review
Action Item: Decide on project feasibility. Prepare Pre-App package, Schedule Pre-App mtg.

Phase II: Pre-Application Meeting
• Submit Pre-App package. Meet with Jurisdiction. Discuss initial findings, potential obstacles & options.
• Post meeting: review possible revisions, variances, or re-designs options
• Hire other professionals (geotech, wetland bio, traffic, landscape arch, etc)
• Applicant could skip the pre-application meeting and move straight to preliminary submittal depending upon jurisdiction and project type
Action Item: Submit Pre-App Package (Application #1). Prepare Preliminary Submittal Package

Phase III: Preliminary Submittal to and Prelim. Approval
• Plat Submittal package and review by agencies planning department
• Complete application  equals a vested project*
• Additional information requests and redline comments
• Work with other jurisdictions (Water & Sewer District, PSE, DOE, etc)
• SEPA determination* (DNS, MDNS, DS EIS)
• Public Hearing
• Issue Preliminary Plat approval with (subject to) conditions
Action Item: Submit Package (Application #2). Respond/Address Jurisdiction comments

Phase IV: Engineering Review
• Engineer will technically design plans for all roads, utilities and other infrastructure to serve project
• Enter development Extension agreements with purveyors
• Approved Engineering plans issued for construction
Action Item: Submit Engineering drawings (Application #3) & redlines

Phase V: Site work construction
• Infrastructure construction
• As-built work & final inspection upon completion with each jurisdiction (Bond as necessary)
Action Item: Hire contractor. Site Inspection & Approval

Phase VI: Final Review & Recording
• Prepare Final Plat maps
• Lot Corner staking
• Redline corrections
• Bond & Final Recording
Action Item: Prepare Final Plat map, Bond & Record


Thanks to Cramer NW http://www.cramernw.com/ for their contribution to this list.