What Every Real Estate Professional Should Know About Land Surveys


A surveyor friend at Site Surveying & Mapping relayed a story about a last minute dilemma they faced that almost killed a closing for a Realtor on a million dollar deal. How did it happen? How could it have been avoided?

Do you ever wonder what type of survey you might need on your site? What are the differences in an ALTA/ACSM and the standards within WAC 332-130? Can I just use the existing survey provided by the Seller?

Having these questions asked over and over lead to the creation of a booklet which will hopefully serve as a good reference for people in understanding Land Surveys as they pertain to the Real Estate Professional.


Link to the full article:
http://www.slideshare.net/JeffMcCann/cfakepathrealtor-and-the-land-surveyor?from=share_email






Thursday, May 6, 2010

All in a day's work


During the final days of their feasibility period to purchase a property, a client requested that I go the Seller’s office to review some documents.

It seems that the Seller had located some additional material that had not previously been disclosed. I was asked to run down and make a quick review of the materials and report back on my findings.

(Note the 21 banker’s boxes of new material)

Wednesday, April 28, 2010

Lot Shortage


Even as foreclosures continue to flood some of the worst-hit housing markets in the country, economists are beginning to sound the warning that today’s extremely low levels of new residential production could lead to significant housing shortages, especially among market-rate rental apartments, as household formation rates return to normal.

The housing downturn and economic recession have kept household formation rates at below-normal levels for roughly three years, said NAHB Chief Economist David Crowe. As the economy moves to higher ground, the housing market will begin to feel the pressure from new households, he said, and there will be a surge of demand from echo boomers, who comprise an even larger group than their baby-boomer parents.

NAHB economists project that the industry will need to deliver 16 million homes over the next 10 years to keep pace with demand. As the excess inventory is worked off, which is likely by the end of 2012, the long-run demand for new housing — based on population growth, immigration and the replacement of losses from the housing stock — will average approximately 1.5 million single-family and 300,000 multifamily units annually, or about 1.8 to 1.9 million total starts.

Coming off extremely low levels of construction, starts last month were running at a seasonally adjusted annual rate of 591,000, a level that is far below what will be needed.

When housing starts bottomed out in the first quarter of 2009, they were running at only 27% of average starts during the “normal” production period of 2000 to 2003, according to analysis by NAHB. This year, production is expected to rise to 45% of normal, with a further increase to 67% of normal next year.

The road back to normal levels of residential construction will be longer for some states than others. By the end of 2011, the top 20% of the states will see their production levels back to normal. Those states include Montana, Wyoming, North Dakota, New Mexico, Kansas, Oklahoma, Texas, Louisiana, Mississippi and Alabama.

So, how long will it take to bring new Lots on-line in the Puget Sound to meet our coming demand? The average nunber of years (from plat application to recording) in King County for single family lots has been 4.75 years!

Average processing time (in years): (Source, New Home Trends)
-----------------------------------------------------------------------------------
King County: 4.75 years
Other Cities in King County: 3.26
Pierce County: 5.44
Other Cities in Pierce County: 3.25
Snohomish County: 3.09
Other Cities in Snohomish: 3.09
Thurston County: 3.09
Other Cities in Thurston County: 2.85

Thursday, March 18, 2010

The Subdivision Process


While every City or County may have its own unique process of subdividing property, most follow a similar general format. I have tried to layout how a typical plot of property might make its way from raw land to finished residential lots.

From Wikipedia
Subdivision is the act of dividing land into pieces that are easier to sell or otherwise develop, usually via a plat. The former single piece as a whole is then known as a subdivision in the United States. If it is used for housing it is typically known as a housing subdivision or housing development, although some developers tend to call these areas communities.
Subdivisions may also be for the purpose of commercial or industrial development, and the results vary from retail malls with independently owned out parcels to industrial parks.


The Subdivision Process

Phase I: Feasibility & Preliminary Preparation
• Review and Research Existing Data & Maps. Recon by consultants as necessary (wetlands, soils etc)
• Initial review of Zoning, Access, Topography, Utilities, Market
• Meet with Jurisdictions
• Preliminary Proforma & Schedule
• Internal Feasibility Results. Proceed or Halt project
• Initial Planning, Hire Engineer
• Field Work (at least enough for submittal): Survey, Mapping, Prelim. Engr., Critical Area review
Action Item: Decide on project feasibility. Prepare Pre-App package, Schedule Pre-App mtg.

Phase II: Pre-Application Meeting
• Submit Pre-App package. Meet with Jurisdiction. Discuss initial findings, potential obstacles & options.
• Post meeting: review possible revisions, variances, or re-designs options
• Hire other professionals (geotech, wetland bio, traffic, landscape arch, etc)
• Applicant could skip the pre-application meeting and move straight to preliminary submittal depending upon jurisdiction and project type
Action Item: Submit Pre-App Package (Application #1). Prepare Preliminary Submittal Package

Phase III: Preliminary Submittal to and Prelim. Approval
• Plat Submittal package and review by agencies planning department
• Complete application  equals a vested project*
• Additional information requests and redline comments
• Work with other jurisdictions (Water & Sewer District, PSE, DOE, etc)
• SEPA determination* (DNS, MDNS, DS EIS)
• Public Hearing
• Issue Preliminary Plat approval with (subject to) conditions
Action Item: Submit Package (Application #2). Respond/Address Jurisdiction comments

Phase IV: Engineering Review
• Engineer will technically design plans for all roads, utilities and other infrastructure to serve project
• Enter development Extension agreements with purveyors
• Approved Engineering plans issued for construction
Action Item: Submit Engineering drawings (Application #3) & redlines

Phase V: Site work construction
• Infrastructure construction
• As-built work & final inspection upon completion with each jurisdiction (Bond as necessary)
Action Item: Hire contractor. Site Inspection & Approval

Phase VI: Final Review & Recording
• Prepare Final Plat maps
• Lot Corner staking
• Redline corrections
• Bond & Final Recording
Action Item: Prepare Final Plat map, Bond & Record


Thanks to Cramer NW http://www.cramernw.com/ for their contribution to this list.